Ninth week, the important jobs of the last 7 days:
Both the external and interior walls have been completed.
All windows have been fitted, including the 'wintergarden' in the front.
The entrance door too it's already here and installed.
The balcony on the first floor is also complete now, next step will be to insulate it and to add the cement.
The roof has also been completed, black tiles are already in place.. Even if in the picture they are white from the ice!
Schedule for next week(s): possibly the external walls will be painted (temperature permitting), and a 'blower door test' to check the insulation of the house.